This guide provides best practices for safely scaling up storage capacity in a VergeOS system by adding drives to existing nodes. It focuses on data security and system resilience through a methodical approach.

Overview

Scaling up a vSAN requires careful planning and execution to ensure minimal disruption to your services. This guide breaks down the process into main phases:

  1. Preparation - Steps to take before your scheduled maintenance window
  2. Pre-Scale Up Verification - Final checks immediately before beginning the scale up
  3. Scale Up Execution - The process of adding and configuring new storage
  4. Post-Scale Up Verification - Ensuring the scale up was successful

Environment-Specific Requirements

This guide covers general best practices. You may need to adapt these steps for your specific environment and requirements.

Prerequisites#

  • Administrative access to VergeOS system
  • IPMI access to all nodes in the cluster
  • New storage drives properly tested and validated
  • Physical access to nodes for drive installation

Preparation Phase#

Complete these steps well before your scheduled maintenance window:

System Readiness#

  • Ensure system snapshot retention is sufficient for potential rollback
  • Set specific success and verification criteria for your workloads

Hardware Preparation#

  • Disks pre-tested in non-production hardware
  • New disks are as large or larger than existing disks
    • And of same performance
  • Verify drive compatibility with existing hardware
  • Ensure you have enough new drives for each member node of the storage tier

Documentation and Planning#

  • Update platform documentation with planned drive additions
  • Document current vSAN configuration for reference
  • Plan communication timeline for affected users
  • Ensure enough time is available for vSAN repair before the storage is required

Resource Verification#

  • Check cluster resource utilization
    • For HCI Systems (combined storage+compute nodes), ensure you have sufficient free memory to reboot 1 node
    • For UCI Systems (dedicated storage nodes) ensure no workloads are running on your storage cluster
  • Confirm network paths among nodes
    • From Node1: Node Diagnostics -> 'Fabric Configuration' reports Core1 and Core2 paths 'confirmed:true' for all nodes
    • From Node2, verify the same
  • Confirm IPMI access to all nodes via a method that allows console access in emergencies

Pre-Scale Up Verification#

Perform these checks on the day of scheduled maintenance, before beginning the scale up:

Current State Verification#

  • Ensure no large storage operations are in progress (VMWare Backups, Imports, NAS file copies, Site Syncs)
  • Resource availability - System is N+1
    • Verify RAM usage is enough to run workloads with a node offline (HCI Systems)
    • Verify vSAN tier being scaled is <70% full
  • Cloud Snapshots are recent and available
    • Set the most recent Snapshot to expire several days in the future for extra retention
  • Confirm Outbound Syncs (if configured) are current
    • Set the most recent remote Snapshot to expire several days in the future for extra retention
  • Verify all vSAN tiers are in a healthy state (green status)
  • Confirm no nodes are pending a reboot
  • Verify Node1 'Fabric Configuration' diagnostic reports Core1 and Core2 paths 'confirmed:true' for all nodes
  • Verify Node2 'Fabric Configuration' diagnostic reports Core1 and Core2 paths 'confirmed:true' for all nodes

Execution Phase#

Adding New Storage#

For detailed step-by-step instructions on performing the vSAN scale up, please refer to:

Scaling Up a vSAN

Key Process Overview#

  1. Put the node in Maintenance Mode (if hot-swap not supported)
  2. Power down target node (if hot-swap not supported)
  3. Install new drives following manufacturer guidelines
  4. Power up node and verify drive detection
  5. Add drives to vSAN tier via VergeOS UI
  6. Monitor tier repair progress - this may take significant time

Critical Wait Period

During the scale up process, the vSAN Tier will show a yellow status during the repair stage. It is essential to wait for the vSAN tier to return to a "green" healthy status before continuing to the next node.

Monitoring Progress

Monitor vSAN repair progress in the VergeOS UI under System -> vSAN. The process will show completion status and available capacity updates.

  1. Repeat for each storage node until complete

Post-Scale Up Verification#

After the scale up completes, verify the system is operating correctly:

System Health Checks#

  • Verify all new drives are recognized and added to the appropriate vSAN tier
  • Confirm increased storage capacity is reflected in the UI
  • Verify vSAN tier shows green status
  • Test/confirm guest systems as required per your success criteria
  • Check logs for any new or unexpected events
  • Verify all success criteria outlined in your preparation steps
  • Confirm data distribution is balanced across all drives

Troubleshooting#

Common Issues#

vSAN tier remains yellow after extended time

  • Verify all new drives are properly seated and detected
  • Check for drive errors in logs
  • Ensure sufficient network bandwidth for repairs
  • Contact support if repairs stall
  • vSAN repairs may take hours, days, or more, depending on many factors like total data stored and drive speed

New drives not detected

  • Verify physical drive installation
  • Check disk controller configuration if applicable
  • Confirm drive compatibility with existing hardware
  • Review system logs for hardware detection issues

Performance degradation during repairs

  • VergeOS makes every effort to prioritize workload storage during repairs
  • Consider minimizing workloads during maintenance window to reduce any possible impact
  • Monitor system resources

Rollback Procedure#

Emergency Support

Should you have any issues with your VergeOS vSAN scale up, please contact our support team for immediate assistance.

Next Steps#

After successful scale up completion:

  • Update capacity planning documentation
  • Adjust monitoring thresholds for new capacity
  • Review backup and snapshot policies for increased data
  • Plan for future scaling needs based on growth projections
  • Schedule follow-up performance monitoring