Pre-Installation Checklist
Hardware readiness, BIOS configuration, boot media creation, network preparation, and planning decisions required before a VergeOS installation.
A successful VergeOS deployment starts well before the first USB drive is plugged in. This page covers every prerequisite you must verify -- from BIOS settings and disk controller modes to switch configuration and boot media preparation -- so that installation day proceeds smoothly and without surprises.
Hardware Readiness
Before scheduling installation, confirm that all physical hardware is racked, cabled, and meets VergeOS requirements.
CPU Requirements
64-bit processor with hardware-assisted virtualization (Intel VT-x or AMD-V)
All processor cores enabled in BIOS
Hyperthreading enabled (recommended for workload density)
Memory Requirements
System reservation per node: 16 GB OS + 1 GB per 1 TB of raw vSAN storage (e.g., a node with 4 TB of raw storage reserves at least 20 GB total)
Plan for workload RAM on top of the system reservation
Disk Controller Configuration
The disk controller is one of the most common sources of installation problems. VergeOS requires direct access to every individual drive -- it does not work with hardware RAID arrays.
HBA (Host Bus Adapter)
Preferred -- passes drives directly to the OS
RAID Controller
Must be set to JBOD / IT mode (passthrough) -- no RAID arrays
NVMe Drives
Verify the controller supports booting from NVMe if all drives are NVMe
Common Pitfall
If drives are configured in a RAID array (even RAID 0), the VergeOS installer will see a single virtual disk instead of individual drives. This prevents proper vSAN tier assignment. Always verify JBOD mode before installation day.
Remote Management (IPMI)
IPMI / iDRAC / iLO ports patched, configured, and tested on every node
Latest IPMI firmware installed (recommended)
Remote console capability verified -- critical for troubleshooting licensing or boot issues during installation
Power
Redundant power supplies connected and configured (recommended for production)
UPS protection for all nodes and network switches
BIOS Configuration
Every node must have its BIOS configured consistently before installation begins. Inconsistent BIOS settings across nodes are a common cause of installation delays.
Boot Mode
UEFI (preferred) or Legacy/Dual
UEFI is required if all drives are NVMe
Hardware Virtualization
Enabled (VT-x / AMD-V)
Required for VergeHV hypervisor operation
Hyperthreading
Enabled
Recommended for workload density
All Processor Cores
Enabled
Do not disable cores to "save power"
Secure Boot
Disabled
VergeOS implements its own boot integrity verification
System Clocks
Set correctly (all nodes within seconds of each other)
Node 1 controls NTP for the entire system after installation
Why Secure Boot Must Be Disabled
VergeOS does not use traditional UEFI Secure Boot. Instead, VergeOS implements its own boot integrity verification that prevents tampered images from booting. This approach provides practical tamper protection without the limitations of UEFI Secure Boot (which requires operating systems to be signed with keys registered in the firmware -- a process controlled by a small number of certificate authorities).
The key difference:
UEFI Secure Boot operates at the firmware level and blocks unsigned operating systems entirely
VergeOS Boot Integrity validates the VergeOS image during boot and refuses to complete if the image has been modified or tampered with
For production environments, this provides equivalent practical security. Any attempt to modify VergeOS system files will be detected and prevent boot. Physical security controls should complement software-level integrity verification.
Hardware Burn-In
Before installation, complete a hardware burn-in to identify early failures:
Verify all drives are visible in BIOS
Confirm all NICs are detected and showing expected MAC addresses
Run vendor diagnostics (Dell BIST, HPE Insight Diagnostics, etc.) if available
Verify MAC addresses match your documentation
Boot Media Creation
The VergeOS installation is delivered as a single ISO image containing all packages for the complete system (hypervisor, storage, networking, and management). You will need a bootable USB drive for each node being installed.
Windows -- Rufus
Download and launch Rufus
Insert a USB drive (it will be overwritten)
Select your USB device under Device
Click Select and choose the VergeOS ISO
Click Start
When prompted, select DD mode -- this is critical
DD Mode is Mandatory
Rufus defaults to ISO mode, but you must select DD mode for VergeOS. Selecting ISO mode will result in an unbootable USB drive. This is the single most common boot media mistake.
macOS -- BalenaEtcher
Download and install BalenaEtcher
Insert a USB drive (it will be overwritten)
Click Flash from file and select the VergeOS ISO
Select the target USB disk (verify you have the correct drive selected)
Click Flash! to start the process
Linux -- USB Image Writer
Navigate to the downloaded ISO file in your file browser
Right-click the ISO and choose Make bootable USB stick (or use
ddfrom the command line)Select the USB drive as the target
Authenticate and write the image
Testing Boot Media
Always test your boot media before installation day:
Boot a test node (or one of the production nodes) from the USB
Verify the VergeOS installer loads into memory and reaches the installation menu
You can safely cancel the installer without making any changes to the system
Network Preparation
Network configuration is the most complex pre-installation task. VergeOS requires two distinct network types, and the physical switches must be configured before installation begins.
Network Architecture Overview
Core Fabric Network
The core fabric is a private, high-speed network carrying vSAN storage traffic, cluster coordination, and VM migration. It is the backbone of the VergeOS system.
Switch port requirements for core fabric:
Port Mode
Access (untagged, single VLAN)
One VLAN per core network
VLAN
Dedicated, isolated VLANs (e.g., 900 for Core1, 901 for Core2)
Must be isolated from ALL other traffic
MTU
9216 (jumbo frames)
Required for storage efficiency and tenant overhead
Spanning Tree
Disabled on core ports
Not needed for dedicated point-to-point core links
Speed
10 Gbps or higher
Minimum recommendation for production
Critical: Do Not Bond Core Fabric NICs
Port bonding (LAG/LACP) must not be used on core fabric networks. VergeOS builds redundancy by using two separate core fabric networks (Core1 and Core2) on separate switches. Bonding would interfere with this built-in redundancy model.
Each core switch must use a dedicated VLAN -- for example, VLAN 900 for Core Fabric 1 and VLAN 901 for Core Fabric 2. These VLANs must be completely isolated from external traffic.
External Network
External networks connect VMs and workloads to users, the internet, and existing infrastructure.
Switch port requirements for external networks:
Port Mode
Trunk (multiple VLANs)
Supports management and workload VLANs
VLANs
Management + workload VLANs as needed
Trunk only the VLANs required
MTU
1500 (standard)
Unless workloads require jumbo frames
Bonding
LACP or Active-Backup (optional)
Recommended for redundancy
NIC Identification
Before installation, map every physical NIC to its intended role:
Absolute minimum: 2 NICs per node -- 1 core fabric + 1 external (a second core fabric NIC is highly recommended, not required)
Recommended: 4+ NICs per node (2 core + 2 external for bonding)
Document the MAC address and physical port location of each NIC
Verify SFP modules are supported by both the NIC and the switch
IP Address Planning
Allocate and document the following before installation:
UI/Management IP address (static, CIDR format -- e.g.,
10.0.0.2/24)Default gateway IP address (test that it is reachable/pingable)
DNS server addresses (at least one, two recommended)
Core fabric VLANs (two dedicated VLANs, documented)
External network VLANs (management + any workload VLANs)
Documentation Requirements
Thorough documentation before installation prevents delays and simplifies troubleshooting. Prepare the following:
A-B Cable Map
Document which NIC on each node connects to which switch and port. Label both ends of every cable.
Rack Elevation
Record the physical position of each node, switch, and PDU in the rack.
Network Design Drawings
Layer 2 (VLAN assignments, trunk/access ports) and Layer 3 (IP subnets, gateways, routing) diagrams.
IP Allocation Spreadsheet
All IP addresses, CIDR masks, gateways, DNS servers, and VLAN IDs in one reference document.
Planning Decisions
Several decisions must be made before installation because they cannot be easily changed afterward:
Encryption (Not Reversible)
VergeOS supports AES-256 at-rest encryption for the vSAN. This decision is made during installation and cannot be changed post-install -- switching from encrypted to unencrypted (or vice versa) requires a full reinstall.
If enabling encryption:
Prepare an encryption key passphrase (8--64 characters)
Prepare a USB drive for each controller node (Nodes 1--2 in an N+1 system; Nodes 1--3 in N+2) to store the encryption key (highly recommended). Other (scale-out) nodes do not require a key drive. An operator can instead type the passphrase at the controller-node boot prompt.
Store the passphrase securely in your password management system
RAM Reservation Preference
During installation planning, decide between two approaches:
More Usable Memory
Allocate more RAM to workloads, accepting slightly reduced HA failover capacity
Stricter N+1 HA
Reserve more RAM for failover scenarios, reducing available workload memory
This setting is configurable post-install but should be planned in advance to match your SLA requirements.
Installation Timeline
Estimated time: 4--8 hours depending on node count and configuration complexity
Schedule a maintenance window with stakeholders
Ensure IPMI/remote access and on-site personnel are available for the entire window
Have VergeOS support contact information ready
Pre-Installation Final Checks (24 Hours Before)
Within 24 hours of the scheduled installation, perform these final verifications:
Summary
Hardware
64-bit CPU with VT-x/AMD-V, 16 GB+ RAM, HBA or JBOD mode, IPMI configured
BIOS
UEFI (required for all-NVMe), virtualization enabled, Secure Boot disabled, clocks synchronized
Boot Media
ISO from VergeOS support, Rufus (DD mode) or BalenaEtcher, tested before install day
Network
Core fabric: dedicated VLANs, MTU 9216, no bonding. External: trunk ports, optional LACP bonding
Documentation
Cable map, rack elevation, network diagrams, IP allocation spreadsheet
Decisions
Encryption (yes/no, not reversible), RAM reservation preference, installation timeline